Project consists of Water Diversion works, prep work in the Impoundment Area, Inter-site Roadworks, 2014 Dam Extension and a Starter Dam Embankment construction. 1,330,000 m3 of Till Fill, 800,000 NAG Rock fill and 1,100,000 m3 of Cycloned Sand.
This is a multi-year project and the project milestone date is July 31, 2013. At October 2012 the expected completion date was 25% ahead of schedule.